Saturday, June 27, 2009

Colour Appointment Done

We had our colour/electrical appointment yesterday which went for about 5 hours. We were exhausted by the end and I think we upgraded quite a bit through the appointment so not really looking forward to seeing the total price.

I have updated the sketch of the front of the house with colours to give an idea of the fascade.

Listed below is the breakdown of some of the items selected.

Externals
Render - Wattyl Wild Yukon

Roof Tiles - Contour Gun Metal Gutters,Downpipes - Colourbond MonumentFascia,Eaves,Posts,Garage - Colourbond Dune Windows - Artic Off white Front Door - Corinthian Infinity Woodgrain Internals
Skirting / Architrave - Wattyl Flokati Bedroom Walls - Wattyl Flokati
Main Walls - Wattyl White Pepper Feature Walls - Wattyl Squire House Doors - Corinthian Impression - Wattyl Flokati

Wednesday, June 17, 2009

Landscape Plan

I have uploaded a copy of the landscape plan we plan on submitting to council. I simply altered the site plan and added references to new and existing trees around the property. The plan is pretty simple as we don't plan on changing much in the backyard in the short term. The front will be made up of a picket fence, some low hedging and a few shrubs.

We are booked in for next Friday to do colour selection, kitchen and electrical!!!




Friday, June 12, 2009

Contract signed

We got our updated tender and thankfully no major surprises. Actually came in cheaper thanks to us not needing an onsite detention system. So signed off on this and paid our deposit.

Took a few weeks to get our updated drawings and everything is looking good except it was missing a few items we previously asked for. You really need an eye for detail when going over plans/tender.

Signed the building Contract today!! 40 week estimated build time with 5 week break at Christmas so we are looking at around 10 months build time. A little peeved they wouldn't increase the late completion payment from $1 a day. Basically take it or leave it.

We also choose our demolition company (State demo) and paid the deposit to them.

We should be doing our colour selection, kitchen and electrical over the next few weeks prior to submitting plans to council. Wish things would move along a bit faster.