Monday, November 29, 2010

Blinds but still not keys

We had our blinds booked in for Thursday last week as we were expecting the keys by then. Our Site supervisor was happy to let us in to get them installed anyway. It appears only a little painting to go now so hopefully keys soon???

Downstairs dining area


Study with ceiling patched after leak

We can finally get a front on pic now the fence and site toilet is gone.


Living area.


Upstairs bedroom


Friday, November 12, 2010

Final inspection. Water leak

We had our final inspection today at 9AM. We found the gas hadn't been connected properly so we couldn't test the HWS or cooktops and found lots of little things that needed to be finished off or touched up with paint. The biggest problem was the water leak we found above the study. The ceiling was all mouldy and when poked with a stick water came pouring out onto the floor. The cause of the leak needs to be looked into and most of the ceiling needs to be replaced. Our site supervisor seems to think they will be able to fix the problems within a week so we can have the keys next Friday but I doubt it. We may have to wait another week.
A few pics from inspection below


Entry. Note: all the bits of blue sticky tape are areas to touched up.


Main Bathroom


View out to backyard. Garden is getting a little overgrown.


Ensuite

Thursday, November 4, 2010

Finally. We have a final inspection date

Friday the 12th Movember is our Final inspection date. We have hired a private building inspector to come through with us just in case we miss anything.
All going well we should have our keys the week after.
I'll post some pictures after the inspection next week.