Saturday, January 30, 2010

Piering Done

Went past the block today and to our suprise they had finished the piering. A few small cracks in some of the concrete but I hear that is normal. Pics below
Front Left.
From the front

View from rear
Rear Alfresco

Split


Left hand side. 1M front and 1.5M rear side setback. Doesn't look like much room for a pathway at the front


Friday, December 25, 2009

Excavation Complete

After one week we are done. Took a little time (and added expense) to get the sandstone out. They needed to bring in some sort of rock saw to get a nice clean cut down the fence line. Finished product looks pretty nice.
We got a bit of a shock when we found out we were up for 23 truck loads of fill removal. Seems a little excessive.





Saturday, December 19, 2009

Excavation Pics


From the back

From the front of the block


Anyone want some Sandstone?


Start of Side cut. Location of retaining wall

Rock saw at work


Wednesday, December 16, 2009

Excavation starts

Just found out they have started excavation already!! Had a call from the supervisor not long ago saying they had hit sandstone(we knew that was coming) and asking whether I was happy with them to remove the sandstone and take the fill.
I wasn't expecting them to start the same day they assigned us a supervisor.

Monday, December 14, 2009

Construction Certificate approved and we have pegs

We received a new hydraulic plan a few weeks ago to fulfil council requirements. Basically we had had to add more trenches to hold more runoff. Not real happy about the extra 7k variation that was added to the contract but what can you do.
Thankfully no major issues getting the construction certificate approved which we found out about last week.
We went out to the block on the weekend and noticed they had done the pegout. Sorry no pictures. I wasn't expecting them in yet.

Wednesday, November 18, 2009

Demolition begins

Demolition started Monday this week and is supposed to finish Wednesday. I will upload some pics when I get them.
We are hoping that our builder will be lodging the Construction certificate this week, but are waiting on the engineers to update the hydraulic plan with some extra detail as per councils condition.
Another condition from council is that we have to build retaining walls as soon possible after excavation. 
The only other condition that really affects us was we needed tree protection for the Gum tree out the front so I had to organise a fence guy to place a fence around the tree for the duration of the build.
We are using an accredited certifier for the construction certificate so hopefully it won’t take as long as council to get approved.


Friday, October 23, 2009

DA Approval Granted

Finally, after 13 weeks we have been told that approval consent has been granted.

After the neighbour submissions and the months it spent in the engineering dept at council we starting to think it would never get approved. The assessing officer mentioned we will have a few special conditions such as tree protection for the Gum trees on the block. We will find out more details about these from the builder next week. Hopefully nothing major.

Demolition is booked in for next month so now I can start ebaying the appliances from around the house.