Sunday, March 28, 2010

More Frames

Had a good look around today and it looks like most of the frames have gone up. A few pics below

Front of the house. Still waiting for garage and porch slabs to be done


View down stairs to the kitchen and dining areas. The blue support should be temporary.

Ensuite and WIR off the main bedroom


Main Bedroom


Back of the house


View out the back. Waiting on Alfresco slab


Lounge/TV area.

Thursday, March 25, 2010

Frames are going up

I can't believe how much things can change in less than a week.
Here are a few pictures snapped from the front. I really need a day when the builders aren't there so I can have a good snoop around.




Saturday, March 20, 2010

Bricking has started

We finally saw some more action at the site this week. It looks like most of the rear foundations have been bricked and have been told the floor joists will be finished next week.
Also received a nasty surprise in the mail of extra expense due to rock excavation while laying the plumbing.

View from the rear.
View of front right.


View of front left. Floor level looks a little higher than we originally thought.

Thursday, February 18, 2010

We have bricks

We managed to catch them unloading the bricks









Sunday, February 14, 2010

External Plumbing Done

Looks like they have finished the external plumbing.
After the huge downpours over the weekend I found the block so muddy I was walking ankle deep in mud in some sections. May need to invest in some gum boots.




Looks like the sewer on the fence line and access points further down the back to the storwater trenchs on the image below. Here's hoping we can hide these under the turf when they are finished.

They've made a bit of a mess of the backyard.
It's going to be a tight squeeze to put a retaining wall next to the grate

Wednesday, February 10, 2010

External Plumbing

Not much happened last week thanks to the rain. The excavators did manage to take away another 3 loads of fill created from the piering/foundations for us.
This week they are back in action working on the external plumbing.


Saturday, January 30, 2010

Piering Done

Went past the block today and to our suprise they had finished the piering. A few small cracks in some of the concrete but I hear that is normal. Pics below
Front Left.
From the front

View from rear
Rear Alfresco

Split


Left hand side. 1M front and 1.5M rear side setback. Doesn't look like much room for a pathway at the front